Pablo Picassostraat · Utrecht

Circulus Utrecht
Build Diary

Living next door while 63 apartments go up — photos and observations from the street.

I'm not obsessed, I just live next door. When something happens I make a picture and have AI update the blog.

ProjectCirculus
Units63 apartments
DeveloperSamen Thuis
ContractorKwakkenbos
CompletionEnd 2027
PhaseFoundation

Week 31, 2026: pile-cap grid fills in, trench and floor slab poured at Circulus Utrecht

2026-07-28

The pile-cap grid at Circulus Utrecht has grown to dozens of blocks, a trench has opened for services by the site cabins, and the first ground-floor slab is being poured between the pile caps. Photos from 28–30 July 2026.

Read more →

Week 30, 2026: ground-beam rebar spreads across the grid, crane swings back in at Circulus Utrecht

2026-07-21

Ground-beam reinforcement now links pile caps across the full Circulus Utrecht grid, and a mobile Heijkoop crane swings back into position – rows of foundation blocks tied together by rebar mats, a mini excavator finishing the rear boundary. Photos from 21 July 2026.

Read more →

Week 29, 2026: formwork set, concrete poured, pile caps revealed at Circulus Utrecht

2026-07-13

Formwork assembled around the rebar cages at Circulus Utrecht on 13 July, then stripped three days later to reveal solid grey concrete pile caps standing in their grid on 16 July. The building's column pattern is now readable from the street. Photos from 13–16 July 2026.

Read more →

Week 28, 2026: rebar cages placed across the full site at Circulus Utrecht

2026-07-07

Prefabricated rebar cages placed across the full Circulus Utrecht foundation pit with a mobile Kraanverhuur crane – workers guiding the steel cages into position as the column grid of the future building becomes readable. Photos from 7 July 2026.

Read more →

Week 27, 2026: pile caps cured and excavation continues at Circulus Utrecht

2026-06-29

Pile caps cured after the first concrete pour at Circulus foundation pit on Pablo Picassostraat Utrecht – square formwork bases, yellow-capped rebar stubs and drainage membrane visible. Photos from 29–30 June 2026.

Read more →

Week 26, 2026: first concrete poured at Circulus Utrecht

2026-06-22

First structural concrete poured at the Circulus foundation pit on Pablo Picassostraat Utrecht – crane arrives, pile caps formed in 36°C heat. Photos and observations from 22–25 June 2026.

Read more →

Week 25, 2026: pile heads cropped, rebar exposed at Circulus Utrecht

2026-06-16

Pile heads cropped and rebar exposed at the Circulus foundation pit, Pablo Picassostraat Utrecht. Red tracked excavator works the sandy pit as the building footprint becomes readable. Photos 16–20 June 2026.

Read more →

Week 24, 2026: pile field and foundation taking shape at Circulus Utrecht

2026-06-08

Full grid of concrete foundation piles exposed at Circulus Utrecht, Pablo Picassostraat. Wellpoint dewatering pump active, two excavators cropping pile heads. Photos 8–11 June 2026.

Read more →

Week 23, 2026: soil removal begins at Circulus Utrecht

2026-06-02

Piling complete at Circulus Utrecht, Pablo Picassostraat. JCB excavator starts soil removal between foundation piles, cables and drainage pipes exposed in the open pit. Photos 2–3 June 2026.

Read more →

Week 19, 2026: CFA piling underway at Circulus Utrecht

2026-05-08

CFA drilling rig from Kuipers Funderingstechnieken bores concrete piles at Circulus Utrecht, Pablo Picassostraat. W. Kool concrete mixer on site, rebar cages staged and ready. Photos 8 May 2026.

Read more →

Week 17, 2026: road closed, Kwakkenbos moves into Pablo Picassostraat

2026-04-22

Pablo Picassostraat road closure takes effect at Circulus Utrecht – Kwakkenbos two-storey site office installed at the corner, access road locked down. This is the street until end of 2027. Photo 22 April 2026.

Read more →

Week 16, 2026: drilling rig arrives at Circulus Utrecht

2026-04-13

First real activity at Circulus Utrecht, Pablo Picassostraat – drilling rig, bigbags and heavy truck on site, Kwakkenbos signage fully installed by end of week. The morning noise from the rig is something else. Photos 13–19 April 2026.

Read more →

Week 15, 2026: road-closure sign installed on Pablo Picassostraat Utrecht

2026-04-08

Road-closure sign on Pablo Picassostraat Utrecht: 'deze weg is afgesloten van 20 apr. t/m 31 dec. 2027' – roughly 20 months of closure ahead for Circulus construction. Installed two weeks before it takes effect. Photo 8 April 2026.

Read more →

Week 12, 2026: fences up, Circulus project announced in Utrecht

2026-03-18

Construction fencing goes up around the lot on Pablo Picassostraat Utrecht, revealing the Circulus project by Samen Thuis, Kwakkenbos and Beumer Nieuwbouw. Photos at dusk, 18 March 2026.

Read more →

Week 45, 2025: playground demolished on Pablo Picassostraat

2025-11-04

An excavator moves in on 4 November 2025 to clear the Pablo Picassostraat neighbourhood playground – the first real sign that the Circulus construction in Utrecht is actually happening.

Read more →

June 2025: the playground that was here before Circulus Utrecht

2025-06-01

The plot on Pablo Picassostraat Utrecht before construction: a neighbourhood playground with basketball hoop, climbing frame and gazebo, photographed June 2025 – months before the Circulus project started.